Estimate concrete for slabs, footings and round columns: cubic yards for ready-mix, a count of pre-mixed bags, or cement, sand and aggregate for site mixing.
A rectangular element is length (A) × width (B) × thickness (C); round shapes use a diameter and a height or depth
Calculator
Calculate concrete volume, bags or materials
Choose how you are buying concrete - ready-mix, bags of pre-mixed concrete, or cement, sand and aggregate to mix yourself - then enter the size of the pour. Every step of the working is shown with the result.
Quick answers
How Much Concrete Do You Need?
Concrete volume
Length × width × thickness, with all three in the same unit. In US units, use feet (divide inches by 12) and divide the cubic feet by 27 for cubic yards; in metric, work in meters to get cubic meters (the form takes some measurements, such as a slab's thickness, in centimeters and converts them). A round shape is π × (diameter ÷ 2)² × height or depth.
Ready-mix
Order that volume plus any waste allowance. A 20 × 10 ft slab 5 in thick is 83.33 ft³; with 5% waste it is 87.5 ft³, or 3.24 yd³.
Pre-mixed bags
Divide the volume by the bag's published yield and round up. A QUIKRETE Concrete Mix No. 1101 80 lb bag yields about 0.6 ft³ - 45 bags per cubic yard - so the same slab takes 146 bags.
Site-mixed materials
Cement, sand and aggregate are bought loose, so the volume is scaled up by a dry-volume factor and split by your mix ratio into cement bags, sand and aggregate. See site-mixed concrete below.
Worked examples
Concrete Calculator Worked Examples
Each example is worked out by the same engine as the calculator, so the same inputs give the same numbers. The waste percentages and prices are illustrative, not recommendations.
One Slab, Three Ways to Buy It
A 20 ft × 10 ft patio slab, 5 in thick, with a 5% waste allowance. The concrete volume is the same in every case; what you buy is not.
The same slab estimated as site-mixed, ready-mix and bagged pre-mix concrete
Footing: four 1.2 m × 1.2 m pad footings, 45 cm deep
Four identical pad footings in metric units with no waste allowance and no water estimate - just the dry materials to buy.
Structure:
Footing
Unit system:
Metric
Length:
1.2 m
Width:
1.2 m
Depth:
45 cm
Quantity:
4
Mix:
1 : 1.5 : 3
Dry-volume factor:
1.54
Wastage:
Blank (0%)
Bag weight:
40 kg
Cement density:
1440 kg/m³
Water:
Not included
Step
Calculation
Result
Wet volume
1.2 m × 1.2 m × (45 cm ÷ 100)
0.648 m³
Quantity
0.648 m³ × 4
2.592 m³
Waste allowance
No waste allowance added (0%)
2.592 m³
Dry volume
2.592 m³ × 1.54 (dry-volume factor)
3.992 m³
Mix parts
1 + 1.5 + 3
5.5 parts (mix 1 : 1.5 : 3)
Cement
3.992 m³ × 1 ÷ 5.5
0.726 m³
Sand
3.992 m³ × 1.5 ÷ 5.5
1.089 m³
Aggregate
3.992 m³ × 3 ÷ 5.5
2.177 m³
Cement weight
0.726 m³ × 1,440 kg/m³
1,045.1 kg (2,304 lb)
Cement bags
1,045.1 kg ÷ 40 kg
26.13 bags, rounded up to 27 bags to buy
Water
Not requested
Not estimated
Site-mixed · rectangular
Column: six 10 ft columns, 12 in × 12 in section
Six square columns using a 94 lb cement bag, a 10% waste allowance and a water estimate. A 12 in × 12 in section is entered as width 1 ft and depth 12 in, because rectangular shapes take two measurements in feet and one in inches.
Structure:
Column
Unit system:
Imperial
Height:
10 ft
Width:
1 ft
Depth:
12 in
Quantity:
6
Mix:
1 : 1.5 : 3
Dry-volume factor:
1.54
Wastage:
10%
Bag weight:
Custom - 94 lb
Cement density:
1440 kg/m³
Water:
Included (w/c 0.45)
Step
Calculation
Result
Wet volume
10 ft × 1 ft × (12 in ÷ 12)
10 ft³ = 0.283 m³
Quantity
10 ft³ × 6
60 ft³ = 1.699 m³
Waste allowance
1.699 m³ × (1 + 10 ÷ 100)
1.869 m³ (66 ft³)
Dry volume
1.869 m³ × 1.54 (dry-volume factor)
2.878 m³ (101.64 ft³)
Mix parts
1 + 1.5 + 3
5.5 parts (mix 1 : 1.5 : 3)
Cement
2.878 m³ × 1 ÷ 5.5
0.523 m³
Sand
2.878 m³ × 1.5 ÷ 5.5
0.785 m³ (27.72 ft³)
Aggregate
2.878 m³ × 3 ÷ 5.5
1.57 m³ (55.44 ft³)
Cement weight
0.523 m³ × 1,440 kg/m³
753.5 kg (1,661.3 lb)
Cement bags
753.5 kg ÷ 94 lb (42.638 kg)
17.67 bags, rounded up to 18 bags to buy
Water
753.5 kg cement × 0.45 (water-cement ratio)
339.1 kg ≈ 339.1 L (89.58 US gal)
Ready-mix · round
Ready-mix round columns: four 40 cm diameter columns, 3 m high
A round shape in metric units, ordered and priced per cubic meter. The diameter is entered in centimeters and the height in meters, as the form shows.
Structure:
Round column
Unit system:
Metric
Diameter:
40 cm
Height:
3 m
Quantity:
4
Wastage:
5%
Price:
190 GBP per m³
Order 2.07 yd³ (1.583 m³, 55.92 ft³) - material cost GBP 300.84, calculated from the full-precision volume (≈ 1.58336 m³).
1Wet volume of one round column: π × (40 cm ÷ 2)² × 3 m = 0.377 m³
2Quantity: 0.377 m³ × 4 = 1.508 m³
3Wastage: 1.508 m³ × (1 + 5 ÷ 100) = 1.583 m³
4Ready-mix order volume: 2.07 yd³ = 1.583 m³ (the waste-adjusted wet volume; no dry-volume factor is applied)
4Pre-mixed bags: 15.551 ft³ ÷ 0.45 ft³ per bag (SAKRETE High-Strength Concrete Mix, 60 lb bag) = 34.56 bags, rounded up to 35 bags to buy
How to use
How to Use the Concrete Calculator
1
Choose how you buy
Choose how you are buying concrete - ready-mix delivered by truck, bags of pre-mixed concrete, or cement, sand and aggregate you mix yourself - and pick Imperial or Metric.
2
Describe the pour
Pick a shape and enter its size: length, width and thickness for a rectangle, or the inside diameter and the height or depth for a round form. Add how many identical pieces you are pouring and, if you want one, a waste allowance.
3
Calculate & check
Select Calculate materials to see the volume and the order quantity or bag count, then open Show calculation to check every step. Add prices if you also want a material-only cost.
Choosing a method
Ready-Mix, Bagged Pre-Mix or Site-Mixed: Which to Choose
Your concrete volume is the same however you buy it - what changes is what you order. Pick the workflow that matches how the concrete will arrive.
The three concrete workflows: when to use each, what you enter and what you get
Workflow
Use it when
You enter
You get
Ready-mix
A truck delivers concrete, ordered by volume.
The shape, size, quantity and an optional waste allowance.
The order volume in cubic yards and cubic meters.
Bagged pre-mix
You buy bags of concrete mix and add water.
A listed bag, or the yield printed on your own bag.
The number of whole bags to buy.
Site-mixed
You buy cement, sand and aggregate and mix them yourself.
A mix ratio, dry-volume factor, cement bag weight, cement density and, optionally, a water-cement ratio.
Cement bags, sand and aggregate volumes, and an optional water estimate.
Measuring
How to Measure Rectangular and Round Pours
Slabs, footings, beams and columns
Measure the length, the width and the finished thickness or depth. Matching pieces - four identical pad footings, say - are one set of measurements with a quantity of four. Split an L-shaped or irregular slab into rectangles and add them up, or find its area first with the Square Footage Calculator.
volume = length × width × thickness
Circular slabs, round columns and round footings
A round shape needs a diameter - the distance straight across, twice the radius - and one other measurement: thickness for a slab, height for a column, depth for a footing. The units differ by shape, and the form shows the unit beside each field.
The waste allowance is applied once, and all three workflows start from the same adjusted volume. Bag counts are rounded up, because you can't buy part of a bag. Volumes are shown in cubic feet, cubic yards and cubic meters using exact NIST conversions (1 yd³ = 27 ft³; 1 ft³ = 0.028316846592 m³; 1 lb = 0.45359237 kg).
Displayed volumes are rounded so they are easy to read, but a cost is worked out from the full-precision volume, not the rounded figure shown. That is why multiplying the rounded 3.24 yd³ by USD 150.00 per cubic yard gives USD 486.00, while the calculator shows USD 486.11.
Site-mixed
Site-Mixed Concrete: Cement, Sand and Aggregate
A nominal mix such as 1 : 2 : 4 is one part cement, two parts sand and four parts coarse aggregate by volume - seven parts in all, so cement is 1/7 of the dry materials, sand 2/7 and aggregate 4/7. Nominal ratios are rules of thumb; they do not guarantee a particular strength. For structural work, use the mix your drawings or engineer specify - structural concrete is normally proportioned by a mix-design procedure and adjusted from trial batches, as described in ACI PRC-211.1.
The dry-volume factor
When you mix concrete yourself you buy the ingredients loose, and loose cement, sand and aggregate take up more room than the finished concrete: there are air gaps between the particles, damp sand bulks up, and a little is lost in handling. The dry-volume factor scales your concrete volume up to the volume of loose ingredients to buy. A factor of 1.54 is widely used for rough nominal-mix estimates; it is an estimating convention, not a published constant, so use your own figure if you have one.
It applies only to site mixing. Ready-mix is ordered by the volume of finished concrete, and a pre-mixed bag's published yield already describes finished concrete, so neither workflow uses it.
Cement density: bulk, not particle
The mix ratio gives cement as a volume, but cement is sold by weight, so the volume is converted with its loose bulk density - the weight of a container of loose powder, air gaps included. 1,440 kg/m³ is a commonly quoted estimating value, and the real figure varies with how settled the powder is. Do not use cement's particle (absolute) density from mix-design tables here: it leaves out the air between particles, is much higher, and would overstate the cement you need.
Mix ratio versus water-cement ratio
The mix ratio is by volume, but the water-cement ratio is a ratio of masses (weights). ACI describes it as the mass of mixing water divided by the mass of cementitious material; cement is the only binder here, so it is water ÷ cement. A ratio of 0.5 means half a kilogram of water for each kilogram of cement (about half a liter). The optional water estimate is cement weight × water-cement ratio. Damp sand and aggregate already carry water, which mix-design procedures adjust for, so follow the water quantity in your specification rather than adding the full estimate on top.
Materials for 1 m³ of finished concrete, worked out by the calculator with a 1.54 dry-volume factor, 1,440 kg/m³ cement density, 50 kg cement bags and no waste. Change either assumption and every figure changes.
Materials per cubic meter of finished concrete for each nominal mix ratio
Mix
Cement
50 kg cement bags
Sand
Aggregate
1 : 1 : 2
554 kg
11.09
0.385 m³ (13.6 ft³)
0.77 m³ (27.2 ft³)
1 : 1.5 : 3
403 kg
8.06
0.42 m³ (14.8 ft³)
0.84 m³ (29.7 ft³)
1 : 2 : 4
317 kg
6.34
0.44 m³ (15.5 ft³)
0.88 m³ (31.1 ft³)
1 : 3 : 6
222 kg
4.44
0.462 m³ (16.3 ft³)
0.924 m³ (32.6 ft³)
1 : 4 : 8
171 kg
3.41
0.474 m³ (16.7 ft³)
0.948 m³ (33.5 ft³)
Ready-mix
Ordering Ready-Mix Concrete
Ready-mix is ordered by the volume of finished concrete - typically cubic yards in the US and cubic meters in metric countries - so the order is simply your adjusted volume. Divide cubic feet by 27 for cubic yards. Do not apply the site-mix dry-volume factor: the supplier batches the dry materials, and at 1.54 the factor would overstate your order by about half.
The calculator does not round your order up to a quarter yard or any other step, because suppliers differ. Ask yours about minimum loads, short-load charges and the increment they batch in.
Bagged pre-mix
Bagged Concrete Mix: How Bag Yields Work
A bag of concrete mix already contains the cement, sand and stone - you add water. Each manufacturer publishes a yield for each bag size: the volume of concrete one bag makes. Treat it as an estimating value for that product and bag size. The calculator divides your volume by that yield and rounds up. No dry-volume factor, mix ratio or cement density is involved.
Yields as published by each manufacturer for these standard mixes (QUIKRETE describes its yields as "approximately" the figure shown), checked against the cited documents on 2026-10-10. Bags per cubic yard is 27 ft³ ÷ yield, before any waste allowance.
Published yield per bag and bags per cubic yard for each listed concrete mix
The listed products are specific QUIKRETE and SAKRETE mixes sold in the US in pound bags. If your bags are 20 kg, 25 kg or any other size, or a fast-setting, high-early-strength or lightweight mix, choose a custom yield and enter the figure the manufacturer publishes for that bag - in liters per bag with Metric selected. Do not work a yield out from the bag weight: mixes of the same weight can yield different volumes.
Cement bags are not concrete mix
A cement bag holds only cement and belongs with the Site-mixed workflow, where you buy sand and aggregate separately. A bag of concrete mix holds everything and is counted by its yield. The calculator keeps their counts, labels and prices separate.
Waste
Choosing a Waste Allowance
A pour rarely uses exactly the calculated volume. An uneven or soft base, forms that bow, spillage and concrete left in the mixer or pump all add to it. There is no single correct percentage, so choose one for your site or ask your supplier or contractor. The calculator adds it once; leave the field blank for none.
On the reference slab, a 5% allowance turns 83.33 ft³ (3.09 yd³) into 87.5 ft³ (3.24 yd³, 2.478 m³).
Cost
Estimating Material Cost
ready-mix = order volume × price per cubic yard or cubic meter
Prices are optional. Sand and aggregate can be priced per cubic yard, cubic meter or cubic foot; the volumes are converted before pricing. The total is the cost of materials only - labor, delivery, tax and equipment are not included - and the currency is a label, with no exchange rate applied.
Practical tips
Measuring and Ordering Tips
Measure the depth in more than one place. Ground is rarely level, so a slab drawn at 4 in may be thinner in one corner and deeper in another. Stretch a string line across the forms, measure down to the compacted base at several points, and enter the average.
Check the real slab thickness, not the board size. Form boards and the slab can differ. Measure from the top of the form or screed line down to the base you will pour on.
Use the inside diameter of round forms. A tube or round form fills from its inside face, so measure across the inside, and enter a diameter - not a radius.
Keep the units straight. Length and width are in feet (or meters) but thickness is in inches (or centimeters). Entering a 5 in slab as 5 ft makes the order twelve times too big.
Base the waste allowance on your site. A soft or uneven base, bowing forms and concrete left in the mixer or pump all add up. Choose a figure for your conditions, or ask your supplier or contractor, and add it once.
Ask your ready-mix supplier about small loads. Many suppliers have a minimum load or charge extra for a short load, and they batch in set increments. Call with your order volume before you book.
Read the yield on the bag you will buy. Yields differ between products and bag sizes. If your bag is not listed, or is a fast-setting or lightweight mix, enter its printed yield as a custom yield.
Know which bag you are buying. "Portland cement" is cement only and goes with the Site-mixed workflow; "concrete mix" already contains sand and gravel and goes with Bagged pre-mix.
Follow the specified water. Adding extra water makes concrete easier to place but weaker. Use the quantity on the bag or in your specification.
Limits
What This Estimate Does Not Cover
This is a quantity estimate from the measurements and assumptions you enter. Real quantities also depend on the mix design, moisture in the sand and aggregate, how the concrete is batched and compacted, and how accurately the forms are set. Strength depends on the mix design, the water-cement ratio - which FHWA describes as the main control of compressive strength, abrasion resistance and permeability - and on placing and curing.
Not a structural design
This calculator handles rectangular and round shapes only. It does not design reinforcement, check loads, size footings, or design beams and columns - that needs a qualified engineer and the applicable building code. The volume taken up by reinforcing steel is not deducted. For the compacted base under a slab, use the Gravel Calculator; to convert bag weights between pounds and kilograms, use the Weight Converter.
Concrete Calculator FAQ
Straight answers on volume, cubic yards, cement bags, bags of concrete mix (including metric bags), round shapes, waste and cost.
How much concrete do I need?
Multiply the length by the width by the thickness. In US units, put all three in feet (divide inches by 12) to get cubic feet, then divide by 27 for cubic yards. In metric, work in meters to get cubic meters; the form lets you enter some measurements, such as a slab's thickness, in centimeters and converts them for you. Multiply by the number of identical pieces and add a waste allowance if you want one. A 20 ft × 10 ft slab 5 inches thick is 83.33 ft³, or about 3.09 yd³ before waste.
How many bags of cement do I need to mix concrete myself?
Choose Site-mixed. Loose cement, sand and aggregate take up more room than finished concrete, so the volume is first scaled up by a dry-volume factor - 1.54 is a widely used estimating figure, not a fixed rule - and then split by your mix ratio. The cement share is converted to a weight using its bulk density and divided by your bag weight, rounding up. For the 20 × 10 ft, 5 in slab at 1 : 2 : 4 with 5% waste, a 1.54 factor, 1,440 kg/m³ and 50 kg bags, that is 16 cement bags (15.7 calculated).
How many 60 lb or 80 lb bags of concrete mix do I need?
Divide your volume in cubic feet by the bag's yield and round up. QUIKRETE Concrete Mix No. 1101 and SAKRETE High-Strength Concrete Mix both list about 0.45 ft³ for a 60 lb bag and about 0.6 ft³ for an 80 lb bag - roughly 60 or 45 bags per cubic yard before waste. The 20 × 10 ft, 5 in slab with 5% waste (87.5 ft³) needs 195 sixty-pound bags or 146 eighty-pound bags.
My concrete bags are 20 kg or 25 kg. What yield should I use?
Use the yield the manufacturer prints on the bag or its data sheet, and enter it as a custom yield - in liters per bag with Metric selected. The QUIKRETE and SAKRETE presets are specific US products sold in pounds, so they will not match bags sold in the UK, Canada or Australia. Do not estimate a yield from the bag weight alone; mixes of the same weight can yield different volumes.
What is the difference between cement and concrete mix?
Cement is the gray powder that binds concrete together; it is only one ingredient. Concrete mix is cement, sand and gravel already blended in the bag, so you only add water. In stores, look for "Portland cement" (cement only) versus "concrete mix". This calculator counts them separately: cement bags in the Site-mixed workflow and pre-mixed bags in the Bagged pre-mix workflow.
How do I work out ready-mix concrete in cubic yards?
Ready-mix is ordered by the volume of finished concrete. Work out the cubic feet, divide by 27, and add your waste allowance. The 20 × 10 ft, 5 in slab is 83.33 ft³; with 5% waste that is 87.5 ft³, or 3.24 yd³ (2.478 m³). The dry-volume factor is not used for ready-mix, and the calculator does not round up to a supplier increment, so ask your supplier about minimum loads.
How do I calculate concrete for a round column, footing or circular slab?
Use π × (diameter ÷ 2)² × height, depth or thickness. Choose Circular slab, Round column or Round footing and the form shows the unit beside each measurement. Use the inside diameter of the form. A 12 in diameter column 10 ft high holds about 7.85 ft³ (0.29 yd³).
How much extra concrete should I allow for waste?
There is no single right percentage. An uneven or soft base, formwork that bows, spillage and concrete left in the mixer or pump all add up, so base the allowance on your site and ask your supplier or contractor. The calculator adds the percentage once, to the volume, and every workflow uses that adjusted figure. Leave it blank for no allowance.
How accurate are the yields printed on concrete bags?
Treat them as estimates, not guarantees. QUIKRETE's data sheet says each bag yields "approximately" the volume listed. SAKRETE's page states a yield for each bag size. Either way, a yield applies only to that product and bag size. The presets cover only the standard mixes in the cited documents. Fast-setting, high-early-strength, lightweight and other specialty mixes can yield differently, so choose a custom yield and enter the figure on your bag. Bag counts are always rounded up.
Can I estimate the cost of the materials?
Yes. Open the optional cost section and enter a price per cubic yard or cubic meter for ready-mix, a price per bag for pre-mixed concrete, or a price per cement bag plus sand and aggregate prices for site-mixed concrete. The result is the material cost only - labor, delivery, tax and equipment are not included - and the currency is just a label, with no exchange rate applied.
Which mix ratio should I use for site-mixed concrete?
Use the mix your drawings, engineer or local code specify. Nominal ratios such as 1 : 2 : 4 (cement : sand : aggregate by volume) are rules of thumb for simple work; they do not guarantee a particular strength. Structural concrete is normally proportioned by a mix-design procedure and adjusted from trial batches, as described in ACI PRC-211.1.
Does this calculator work out concrete strength?
No. It estimates quantities only. Strength depends on the mix design, the water-cement ratio, the materials, placing and curing - FHWA describes the water-cement ratio as the main control of compressive strength, abrasion resistance and permeability. Reinforcement, loads and the size of footings, beams and columns need a qualified engineer and the applicable building code.